Getting a building permit in Chicago
How a Chicago building permit works: the Department of Buildings, E-Plan online submissions, fees, inspections, licensed trades, and when zoning applies.
Before a Chicago owner or contractor builds, adds, rewires or remodels in a way that affects a building's structure or its systems, the work usually needs a permit from the city. The permit office is the Department of Buildings, which handles permits, inspections, trade licensing and code enforcement. A different department, Planning and Development, handles zoning, and the two reviews are not the same thing. Understanding which question belongs to which department is the quickest way to get through the process without redoing plans.
This guide describes the order of the process. It does not tell you whether a specific project needs a permit, since that depends on the work and the building. For that, the department answers questions directly, at 312.744.3449, or at its office at City Hall, 121 N. LaSalle St., Room 900.
Two reviews: zoning and building
Zoning asks what the property is allowed to be used for and how big a building can be: use, height, setbacks, lot coverage and similar rules. In Chicago the Department of Planning and Development, at 121 N. LaSalle St., 10th Floor, 312.744.4190, handles zoning, along with planning, historic preservation and tax increment financing. A project that adds a unit, changes a building's use or adds a large structure raises a zoning question first.
Building asks whether the work meets the building code: structural soundness, fire safety, electrical, plumbing, mechanical systems and accessibility. The Department of Buildings reviews plans against the code, issues the permit and inspects the work.
A practical order for an owner: confirm the zoning allows what you plan, then prepare plans for the permit. If the zoning does not allow it, the project can change before you pay for drawings. Ask both departments early, and ask in writing so you have a record of what you were told. See also Chicago Department of Buildings and Chicago Department of Planning and Development.
Steps for a typical permit
- Define the scope. Write down what you plan to do: a new bathroom, a rear porch, a basement conversion, a new electrical panel, a new roof. The scope decides the permit type and which trades are involved.
- Check zoning if the work changes the footprint, the number of units or the use. Contact Planning and Development.
- Hire licensed people where the law requires. The department handles trade licensing, which is the process by which electricians, plumbers and other trades are licensed in the city. Ask any contractor you hire for their license and permit history, and confirm that they will pull the permit in their name and your address.
- Prepare plans. Larger projects need drawings from a design professional. Smaller repairs may need less. The department's pages list what each permit type requires.
- Submit through E-Plan. The Department of Buildings runs an online submission platform called E-Plan, which lets applicants submit plans and permit applications and follow the review. Submitting online saves a trip to City Hall for many applications, though some permits and questions are still handled in person.
- Pay the fee. The department has a permit fee calculator on its website. Fees depend on the type and size of the work, so this guide does not quote them. Use the calculator for an estimate before you commit.
- Respond to plan review comments. Reviewers may ask for changes. Answer them in the system and resubmit.
- Receive and post the permit. Keep the permit where inspectors can see it, usually at the site.
- Schedule inspections. The work is inspected at stages, such as rough-in work before walls are closed, and again at completion. Do not close walls or cover work before an inspector has seen it if the permit requires it. A failed inspection means correcting the item and scheduling another.
- Final sign-off. Once the work passes, the permit is closed. Keep the paperwork, since a buyer or lender will ask for it later.
Why the paperwork matters later
A permit is not only a fee. It creates a record that the work was reviewed and inspected. When you sell a house, a buyer's attorney or inspector may look at the city's permit record, and open permits or work with no permit can complicate a sale. See Buying a home in Chicago: the steps for the buyer's side. For an owner, closing out each permit with a final inspection is worth the effort.
Unpermitted work is also a safety matter. Electrical, gas and structural work done without review can create hazards. This guide is general, not legal or insurance advice; ask your insurer how it treats unpermitted work.
Who can pull a permit
Some permits can be pulled by the owner for work on an owner-occupied home, and others require a licensed contractor or a design professional. The rules depend on the trade and the building, and the department's permit pages list them. When a contractor tells you that you do not need a permit, ask them to point to the department's page that says so.
If you see work without a permit
Neighbors sometimes see construction that looks as if it has no permit sign. Chicago residents can report a building problem through 311, and the report is routed to the Department of Buildings for inspection. A stop-work order can follow if the work lacks a permit. Use the 311 phone line or CHI311 app; see Using 311 and the CHI311 app. Tenants who live in a building with unsafe conditions can also report to 311. The rental side of repairs is in Renting in Chicago: what to know before you sign.
Businesses and permits
A business that opens a storefront often needs both a business license and a building permit for any build-out, with a zoning check and an inspection before opening. The sequence matters because the license application may depend on a passed inspection. See Licensing a small business in Chicago.
Where to start
- Questions about a permit: the Department of Buildings, 312.744.3449.
- Zoning questions: the Department of Planning and Development, 312.744.4190.
- Submissions and fee estimates: the department's E-Plan and fee calculator pages at chicago.gov.
- Complaints about work or conditions: 311.
Permits and rules change, and the department's own pages are the authority. Take the project name, address and scope with you when you call.