Most floods start with rain. This one started with a pile driver. On Monday, April 13, 1992, a crew replacing pilings beside the Kinzie Street bridge on the Chicago River drove one into the riverbed near an old, forgotten tunnel. The tunnel's wall gave way, and the river began pouring through the hole into the network of abandoned freight tunnels that ran under the downtown streets. About 250 million gallons of water ended up in the basements of the Loop and in the underground pedestrian walkways, and the central business district was evacuated. For scale, a typical Olympic-size swimming pool holds about 660,000 gallons, so what came through that hole would have filled roughly 380 of them.
The event has several names. Insurers classified it as a leak, which is why plenty of Chicagoans call it the "Great Chicago Leak." It cost an estimated $1.95 billion in 1992 dollars.
The tunnels under the Loop
Under the downtown streets lay a second city most people had forgotten. In the early 1900s a company had dug a network of narrow tunnels beneath the central district to carry freight by small railway, so goods could move below the crowded streets. The tunnels were long out of use by 1992. They were still there, tied into the basements of many downtown buildings, and nobody could say for certain who owned them or who answered for them. The tunnels had once had flood doors to isolate sections if water got in. The doors had been removed years earlier.
An empty tunnel network wired into basements, no doors, no clear owner: that combination is why a small break became a major flood.
How the hole opened
The crew was working on the Kinzie Street bridge, which crosses the river at the north end of the Loop. A piling was driven into the riverbed next to the old tunnel. The pressure pushed aside the clay around it, and over time the tunnel wall was breached. Clay that had held back the water liquefied, and the flow picked up.
A telecommunications worker underground found the leak and sent a videotape of it to the city. The city did not at first see a serious problem. The tunnels were poorly documented, and ownership was unclear, so there was no obvious person in charge. In the hours that followed, the leak grew.
The Loop empties
As water ran through the tunnels and into basements, things got worse through the morning. The Loop was evacuated, and electricity and gas were turned off in the affected area as a precaution. Trading at the Board of Trade and the Mercantile Exchange ended mid-morning. Basements of department stores, office towers and city buildings filled. In some of the lowest levels the water stood as deep as 40 feet. The underground Pedway, the system of walkways linking buildings below the surface, flooded too.
For tens of thousands of workers and shoppers the day became a scramble to get out of the district. Power and heat were out in many buildings for days, and the city had to work out how to stop the water, how to pump it out and how to tell which buildings were safe.
Plugging the hole
The repair had to start with the river. Crews lowered the level of the Chicago River so less water would pour through the breach. Then workers dumped 65 truckloads of rocks, cement and old mattresses into the hole to slow it. With the river down and the flow slowed, they drained the freight tunnels and sealed the leak with a fast-setting concrete mixture.
Draining the tunnels took days. The agencies that handle water and emergencies in the city today are described in Chicago Department of Water Management and Office of Emergency Management and Communications.
How long it lasted
Business in the Loop resumed after about three days. Some buildings stayed closed for weeks, as owners pumped out basements, replaced electrical equipment and inspected structures. The total cost was estimated at $1.95 billion in 1992 dollars.
Leak or flood?
What to call it had consequences. Insurance policies commonly covered damage from leaks but not from floods, and the event was classified as a leak. That is why many residents call it the Great Chicago Leak, and it is why the dispute over insurance and responsibility got so tangled.
Who was responsible?
Lawsuits followed. The company whose crews had driven the pilings, Great Lakes Dredge and Dock, was at first found liable. It was later cleared, on the grounds that the city knew the tunnel was leaking and had not maintained it. In 1995 the Supreme Court decided a related case, known as Grubart, holding that admiralty law applied, which greatly limited the company's liability. It is a reminder that even a disaster with one apparent cause can raise questions about maintenance, ownership and law that take years to resolve.
What the city did afterward
The city took over maintenance of the tunnels and installed watertight hatches to prevent a repeat. The tunnels are no longer an unowned space under the Loop.
Why basements and the Pedway took the water
Water takes the lowest path. The freight tunnels ran below the basements of many downtown buildings and were joined to some of them by old openings, so water entering the tunnels rose through those connections into the lowest levels of the buildings above. The Pedway, a system of underground walkways that lets pedestrians cross downtown out of the weather, sits at a similar depth and flooded with them. For a day or two large parts of the city's underground life, including mechanical rooms, parking levels, shops and walkways, were under water.
In many buildings the basement is where the electrical switchgear, boilers and elevator machinery live, and that is a large part of why recovery took so long. A flooded basement is not just a wet room: it is a building without power, heat or working elevators until the equipment has been dried, tested or replaced.
A short glossary
- Piling. A long column of timber, steel or concrete driven into the ground or riverbed to support a structure, in this case work on the Kinzie Street bridge.
- Freight tunnels. The narrow railway tunnels dug beneath downtown streets in the early twentieth century, abandoned long before 1992.
- Pedway. The network of underground and enclosed walkways linking buildings in the central district.
- Admiralty law. The body of law that governs accidents on navigable waters, which the Supreme Court applied to the case in 1995.
- Liquefaction. The loss of strength of soil when it is saturated and disturbed, so it flows like a liquid, as the clay did around the breach.
What owners and residents can learn
The flood is a case study in preparing for water, and the lessons apply at any scale:
- Know where water can enter a building or a block, including from below, and where the lowest level is.
- Know who is responsible for infrastructure that touches your property. In 1992 that question was unanswered.
- Keep critical equipment above the lowest level where possible, and know where the shutoffs for power, gas and water are.
- Have a plan for getting out, and know more than one route.
- Report problems early. A leak was found and videotaped before it became a flood, but it was not taken seriously at once.
The practical steps for households are in Emergency preparedness in Chicago.
The river and the city's long fight with water
The 1992 flood is one episode in a long story. The city was built on low ground and in the 1850s raised its streets by four to five feet (see raising the city out of the mud: the 1856 grade decision). In 1900 the river's flow was reversed (see Reversing the river: the Sanitary and Ship Canal). Today the region manages heavy rain with a system of deep tunnels (see flash flooding and the region's stormwater system). The 1992 flood was different in kind, because it came from a human error rather than from weather, but it belongs to the same record of a place where the water is never far away.
The flood in dates
| Date | Event |
|---|---|
| Early 1900s | A network of freight tunnels is built under the Loop |
| Years before 1992 | The flood doors in the tunnels are removed |
| April 13, 1992 | Repair work at the Kinzie Street bridge breaches a tunnel wall; the Loop is evacuated |
| Mid-morning | Trading ends at the Board of Trade and the Mercantile Exchange |
| About three days later | Business resumes |
| 1995 | The Supreme Court's Grubart decision applies admiralty law |
What it teaches
Several lessons stand out.
- Know what is underneath. The tunnels were part of the city's infrastructure, and nobody was clearly in charge of them.
- Small repairs can have large effects. A single piling was enough to start a flood that closed the center of the city.
- Ownership matters. In the first hours, the lack of a responsible party slowed the response.
- Preparedness is local. The advice for households and businesses is in Emergency preparedness in Chicago.
For the physical setting, the river and its bridges, see Why Chicago has so many movable bridges and The Chicago River from the Riverwalk. A walking tour of the Loop's streets above the tunnels is in A walk under the Loop elevated, block by block, and the neighborhood is described in The Loop. For how the region handles heavy rain today, see flash flooding and the region's stormwater system.
Questions people ask
What caused it? A piling driven near an old freight tunnel during bridge repair breached the tunnel wall.
How much water? About 250 million gallons.
Why is it called a leak? Insurance covered leaks but not floods, and the event was classified as a leak.